Article VIII

What is Article VIII?

Effective April 20, 2024, the Renewable Action through Project Interconnection and Development (RAPID) Act (L 2024, ch 58, part O) repealed Executive Law § 94-c, repealed the current Public Service Law article VIII, and enacted a new Public Service Law article VIII entitled “Siting of Renewable Energy and Electric Transmission” (Article VIII). The RAPID Act also transferred the Office of Renewable Energy Siting (ORES) from the Department of State to the Department of Public Service, continuing all existing functions, powers, duties, and obligations related to major electric transmission siting.

With respect to ORES’s regulations at 19 NYCRR part 900, the RAPID Act transfers part 900 to 16 NYCRR chapter XI and continues part 900 in full force and effect subject to conforming changes, such as the substitution of numbering, names, titles, citations, and other non-substantive changes to be filed with the Secretary of State (see RAPID Act §7). The conforming changes were filed with the Secretary of State as a new Part 1100 of Title 16 of the NYCRR and became effective July 17, 2024. Article VIII and the former 19 NYCRR Part 900 (Section 94-c) provide for the State’s consolidated review and permitting process for major renewable energy facilities (25 megawatts or larger).

Office of Renewable Energy Siting

Article VIII places the review and permitting of such facilities into a single forum, the Office of Renewable Energy Siting (ORES). ORES has the authority to issue a single permit for the construction of major renewable energy facilities from both a state and local law perspective. ORES takes into consideration local laws, public health and safety, environmental, social and economic factors pertinent in deciding to permit such facilities.

Article VIII Permitting Process

  • The Article VIII process contains pre-application public engagement with the local community, pre-application consultations with state agencies and local municipalities, application review, draft permit, hearings and decision, and compliance.
  • Projects must be designed to avoid or minimize, to the maximum extent practicable, potentially significant adverse environmental impacts.
  • Article VIII requires that the final decision on a project’s permit be made within one year of the application being completed.
  • Only projects with “substantive and significant” issues require evidentiary hearings, testimony and briefing.
  • Projects are required to comply with substantive provisions of applicable local laws and regulations. ORES can elect not to apply a local law that is unreasonably burdensome in view of CLCPA targets and environmental benefits of the project.
  • Prior to submitting a permit application, renewable energy projects are required to consult with the host municipalities and communities in which the proposed project will be located.
  • ORES also requires that state agencies are consulted and subsequently review and approve decisions involving wetland and stream delineations, threatened and endangered species, and archeological and cultural resources, if appropriate. Agency consultations should take place at the earliest point possible in the applicant’s process.
  • Following consultations with impacted agencies, Article VIII applicants must hold at least one meeting for community members. Notice of the meeting should be provided to community members no sooner than 21 days before the meeting takes place, and no later than 14 days before the meeting takes place. Included in an Article VIII application are copies of meeting transcripts, materials, and discussions. Notice of intent to file an application should be published by the applicant at least 60 days before the application is filed.
  • Municipalities are notified upon ORES issuance of draft permit conditions and are required to provide feedback on the draft permit conditions and compliance with local laws. In addition, there is a 60-day public comment period following the publishing of the draft permit.
  • Outside of the Article VIII public comment period and requirements, Mill Point Solar is committed to continually engaging with the community and considering input. Project representatives are regularly attending Glen Town Board meetings and Planning Board meetings to provide project updates and answer questions. In addition, the project website has project information, frequently asked questions, and contact information, as well as a form through which comments can be submitted.

Exhibits required as part of an Article VII Application include summaries, third-party reports, and information on the following topics:

  • General Requirements
  • Overview and Public Involvement
  • Location of Facilities and Surrounding Land Use
  • Real Property
  • Design Drawings
  • Public Health, Safety and Security
  • Noise and Vibration
  • Visual Impacts
  • Cultural Resources
  • Geology, Seismology, and Soils
  • Terrestrial Ecology
  • NYS Threatened and Endangered Species
  • Water Resources and Aquatic Ecology
  • Wetlands
  • Agricultural Resources
  • Effect on Transportation
  • Consistency with Energy Planning Objectives
  • Socioeconomic Effects
  • Environmental Justice
  • Effect on Communications
  • Electric System Effects and Interconnection
  • Electric and Magnetic Fields
  • Site Restoration and Decommissioning
  • Local Laws and Other Ordinances
  • Other Permits and Approvals

Once the project is certified, there is a three-part compliance phase:

  • Pre-Construction – filing of engineering and design documents, permits, and approvals prior to construction
  • On-Site Compliance – on-site inspections by state agency personnel after construction begins to ensure the project is complying with the Certificate
  • Long-Term Compliance – on-site inspections regarding the operation of the facility over its lifetime

Local Agency Account Funding: Mill Point Solar I Project

Local agency account funding is money that Applicants (i.e.,) make available to qualified, locally affected parties and municipalities to offset certain expenses they incur in participating in the state permitting process. These funds are meant to encourage early and effective public involvement in project development and permitting.

Upon the filing of an Article VIII Application, Repsol Renewables will post $1,000/MW, a total of $250,000.00 for the Mill Point Solar Project, which can be sought by local community members and the Town of Glen. 75% of local agency account funds are reserved for municipalities under Article VIII.

Qualified, locally affected parties may apply for funds within 30 days of Application filing by submitting an application to:

Attention: Request for Local Agency Account Funding 
Office of Renewable Energy Siting 
Empire State Plaza 
240 State Street 
P-1 South, J Dock 
Albany, NY 12242 

How to request party status for an Article VIII proceeding

In order to formally file papers related to issues of fact and have them considered as part of the evidentiary record, you must be granted full party or amicus status pursuant to Section 1100-8.4 of the Article VIII regulations. The period for filing a petition for party status shall be at least sixty (60) days from the Office of Hearing’s issuance of notice of the public comment hearing.  Nonparties who wish to have their comments recorded are permitted to submit oral or written comments during the public comment portion of the proceedings, or as otherwise provided by the ALJ. Such public statements will not constitute evidence in the adjudicatory hearing but may be used by the ALJ as a basis for further inquiries.

To request full party or amicus status, an interested party should file a written petition and complete one of the following two options:

For full party status, interested parties should file a petition that includes:

For amicus party status, interested parties should file a petition that includes:

Public Documents and Information: Mill Point Solar I Project

Stakeholder involvement and consultation are part of an ongoing, evolving process throughout all phases of the Article VIII review process. Repsol Renewables’ goal is to provide information to stakeholders, understand stakeholder interests, identify any additional stakeholders potentially affected by the Mill Point Solar I Project, solicit information from stakeholders during public outreach events and generally foster public participation in the Article VIII review process.

You may access all documents electronically through the links above and on ORES’s Document Matter Manager (DMM), or you may access hard copies of the documents at one of the following locations:

Glen Town Clerk’s Office

7 Erie Street
Fultonville, NY 12072

MON–FRI: 8am-2pm; TUES, 6pm as directed by the court

Frothingham Free Library
28 West Main Street
Fonda, NY 12068

MON–WED: 10am–6pm; FRI: 10am–6pm; SAT: 9am–12pm

To view the Mill Point Solar I Project’s Article VIII application, click here.

Please note: as additional documents are filed, this section will be updated.

Public Comment

Any party wishing to remain a party under the Article VIII process is encouraged to review the draft Article VIII regulations and to contact the ORES office with any questions at: general@ores.ny.gov.

To stay up to date about the Mill Point Solar I Project, please join our stakeholder notification list by filling out the contact form here. You can also call us at (866) 203-1118 or email us at info@millpointsolar.com.